Which of the following is a characteristics of a matrix organization?
Answer(s): D
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 56
A WBS is being developed for a project.Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
Answer(s): B
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.Which of the following documents should the project manager use to obtain this information?
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 328
A stakeholder is unaware of a project’s status.Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
Answer(s): A,D
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
There are four parallel paths on a network diagram. The summary duration of each path is below:A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeksWhich of the following tasks are on the critical path?
Answer(s): C
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175