A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.

Which of the following techniques is MOST likely to be used to complete the project on time?

  1. Throttling
  2. Crashing
  3. Resource leveling
  4. Resource smoothing

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170



A project manager is unsure if the quality of a deliverable from a SME meets specifications. Which of the following is the BEST way for the project manager to address the issue?

  1. Conduct a face-to-face or telephone meeting with the team member.
  2. Send an email outlining the concerns to the team member.
  3. Send a project team meeting to obtain feedback from everyone.
  4. Post the issue on the wiki page for input from stakeholders.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261



Which of the following is a key aspect of the Agile project management methodology?

  1. Test-driven
  2. Daily standup meetings
  3. Short project durations
  4. Defined list of requirements

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286



A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?

  1. Assess the risk register’s new items.
  2. Review the task start and finish dates.
  3. Obtain additional resources.
  4. Analyze the assigned hours.

Answer(s): A



A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements.
Which of the following actions would be BEST for the project manager to take?

  1. Ask the client to provide additional language resources to the team.
  2. Purchase a language translation program.
  3. Hire a translator to help the key team member
  4. Ask the client to provide requirements in the native language of the team.

Answer(s): D