During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?

  1. Business case
  2. Requirements document
  3. Project timeline
  4. Task plan

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138



A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.

Which of the following should a project manager update to document this information?

  1. A list of realized risks
  2. A list of decomposed activities
  3. A sequenced list of project tasks
  4. A document describing agreed-upon communication methods

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240



The executive sponsor asks a project manager to summarize the following for a project:

1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.

Which of the following information should the project manager provide?

  1. Cost baseline
  2. Burn rate
  3. Cost variance report
  4. Total project cost

Answer(s): A



Which of the following defines a group of projects that work together to achieve a common goal?

  1. Product
  2. Portfolio
  3. Program
  4. Project plan

Answer(s): C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71






Post your Comments and Discuss CompTIA PK0-004 exam prep with other Community members:

PK0-004 Exam Discussions & Posts