CompTIA PK0-004 Exam Questions
CompTIA Project+ (Page 8 )

Updated On: 15-Feb-2026

After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?

  1. Use milestones identified in the project charter.
  2. Use data based on past knowledge.
  3. Hold a full team workshop to review the complete WBS.
  4. Collaborate with other project managers.

Answer(s): A



A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?

  1. Outsourcing
  2. Business acquisition
  3. Business process change
  4. Internal reorganization

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297



A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.
Which of the following constraints are MOST likely to be affected? (Choose two.)

  1. Quality because the existing system is now outside the threshold.
  2. Requirements because this is a change to initial scope.
  3. Cost because replacing the system incurs additional expense.
  4. Schedule because this was an unscheduled task and will impact the timeline.
  5. Stakeholders because they will need to understand the modification and provide buy-in.

Answer(s): C,D


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293



Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

  1. SCRUM retrospective
  2. Kickoff meeting
  3. Budget baseline
  4. Risk review

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306



The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

  1. Balanced score card
  2. WBS
  3. Post-project evaluation
  4. PERT

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 332






Post your Comments and Discuss CompTIA PK0-004 exam dumps with other Community members:

Join the PK0-004 Discussion