A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Choose two.)

  1. Risk report
  2. Defect log
  3. Issue log
  4. Backlog
  5. Change log
  6. Progress report

Answer(s): D,E



A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

  1. SOW
  2. RFI
  3. RFQ
  4. WBS

Answer(s): A



During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

  1. Determine budget constraints.
  2. Validate the business case.
  3. Update the project charter.
  4. Create a project schedule.

Answer(s): C



A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

  1. Scope creep
  2. Collecting requirements
  3. Decision-making
  4. Project change

Answer(s): A



Which of the following BEST illustrates how team members with different roles should interact on the team?

  1. SOW
  2. WBS
  3. RACI
  4. PERT

Answer(s): C



For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

  1. Resource plan
  2. Organizational chart
  3. Project charter
  4. RACI chart

Answer(s): D



Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

  1. Kanban board
  2. Pareto chart
  3. Ishikawa diagram
  4. Decision tree

Answer(s): C



A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

  1. Dashboard
  2. Gantt chart
  3. Work breakdown structure
  4. Requirements Traceability Matrix

Answer(s): A