A critical business initiative introduced new processes and technology to the organization.
Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

  1. Creation of a social news forum
  2. Management directives to use the new system
  3. New user kickoff meeting
  4. Monthly feedback and training sessions

Answer(s): D



A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:



Based on the chart, which of the following is the current status of the project?

  1. Behind schedule and over budget
  2. Behind schedule and under budget
  3. Ahead of schedule and over budget
  4. Ahead of schedule and under budget

Answer(s): A



Which of the following criteria would favor using the agile methodology to manage an upcoming project?

  1. Strong projectized organization
  2. Medium risk
  3. Lack of resources
  4. Multiple undefined tasks

Answer(s): D



A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
· Purpose
· Scope of work
· Location of work
· Period of performance
· Deliverables schedule
· Applicable standards
· Acceptance criteria
· Special requirements
· Payment schedule
Which of the following documents did the client provide to the project manager?

  1. RFP
  2. WBS
  3. SLA
  4. SOW

Answer(s): D



While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time- consuming project was executed previously in the organization.
Which of the following actions should the PM take?

  1. Perform a root cause analysis.
  2. Organize a stakeholder meeting
  3. Escalate the issue to the CCB
  4. Contact the PMO for assistance.

Answer(s): D