Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

  1. Smoke testing
  2. Regression testing
  3. Unit testing
  4. User acceptance testing

Answer(s): B



A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

  1. Secure folder
  2. Real-time, multiauthoring editing software
  3. Digital whiteboard
  4. Wiki knowledge base

Answer(s): D



During online, collaborative meeting sessions, a project team is consistently in consensus, which is causing a creativity roadblock. Which of the following can the facilitator do to minimize this issue?

  1. Enable chat.
  2. Distribute surveys.
  3. Meet face to face.
  4. Use a whiteboard.

Answer(s): D



During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?

  1. Waterfall method
  2. Simulation method
  3. Precedence diagramming method
  4. Critical path method

Answer(s): C



During an audit, a project manager finds out that a contractor exceeded the overtime hours allowed by the contract. Which of the following tools should the PM use to share the details with the management team?

  1. Time-tracking log
  2. Issue log
  3. Statement of work
  4. Risk register

Answer(s): A



A segment of a project has ended. Before moving on to the next segment, the project manager wants to assess if the work produced in the previous segment meets a high enough standard and if adequate resources are available to continue the project. Which of the following should the project manager do?

  1. Review the progress reports.
  2. Perform a gap analysis.
  3. Coordinate a phase-gate review.
  4. Set up touch points with the team.

Answer(s): C



Which of the following can be used to determine whether a sample product is within an acceptable range?

  1. Scatter diagram
  2. Velocity chart
  3. Control chart
  4. Fishbone diagram

Answer(s): C



A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take?

  1. Continue to monitor the system performance.
  2. Resize the resource utilization to reflect current needs.
  3. Reinforce adoption over time.
  4. Raise an item in the issue log.

Answer(s): B