A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

  1. Create a list of tasks and share it with the team.
  2. Resend the scope of work to the team.
  3. Review the Gantt chart weekly with the team.
  4. Have the project sponsor meet with the team.

Answer(s): A



A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

  1. Make an impact assessment.
  2. Prepare a new purchase order.
  3. Select a new vendor.
  4. Create a risk register.

Answer(s): A



Which of the following BEST identifies the intent and purpose of a project closeout report?

  1. To provide documentation of lessons learned
  2. To document variances from the initial project baseline
  3. To validate that a project has been successfully completed
  4. To release resources and terminate all access rights

Answer(s): C



A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

  1. ROI.
  2. SOW.
  3. RFI.
  4. RFP.

Answer(s): A



Page 16 of 53



Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:

Jack commented on October 18, 2024
are these legit ?
Anonymous
upvote

samsam commented on September 11, 2024
i hope this will help me pass
Anonymous
upvote

Joe commented on March 26, 2024
it helped me pass
Anonymous
upvote