Which of the following BEST illustrates how team members with different roles should interact on the team?

  1. SOW
  2. WBS
  3. RACI
  4. PERT

Answer(s): C



For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

  1. Resource plan
  2. Organizational chart
  3. Project charter
  4. RACI chart

Answer(s): D



Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

  1. Kanban board
  2. Pareto chart
  3. Ishikawa diagram
  4. Decision tree

Answer(s): C



A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

  1. Dashboard
  2. Gantt chart
  3. Work breakdown structure
  4. Requirements Traceability Matrix

Answer(s): A



Page 18 of 53



Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:

Jack commented on October 18, 2024
are these legit ?
Anonymous
upvote

samsam commented on September 11, 2024
i hope this will help me pass
Anonymous
upvote

Joe commented on March 26, 2024
it helped me pass
Anonymous
upvote