As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

  1. Update the work breakdown structure.
  2. Review the backlog.
  3. Seek baseline approval.
  4. Establish the resource pool.

Answer(s): C



A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

  1. Trigger the contingency plan and communicate with the stakeholders.
  2. Work with the functional managers to create a work-around.
  3. Submit a change request to the change control board.
  4. Transfer the risk by hiring a new vendor who was successful on a previous project.
  5. Set up an escalation meeting with the sponsor.

Answer(s): C



By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

  1. Allocate resources. Most Voted
  2. Determine the project budget.
  3. Develop a communication plan.
  4. Establish baselines.

Answer(s): A



A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

  1. RFI
  2. RACI
  3. WBS
  4. SOW

Answer(s): B



Page 3 of 53



Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:

Jack commented on October 18, 2024
are these legit ?
Anonymous
upvote

samsam commented on September 11, 2024
i hope this will help me pass
Anonymous
upvote

Joe commented on March 26, 2024
it helped me pass
Anonymous
upvote