A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
Answer(s): A
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
Answer(s): C
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
Answer(s): D
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
Answer(s): B