A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager. Which of the following should the newly appointed project manager do next?

  1. Conduct a risk assessment.
  2. Create a project scope document.
  3. Identify stakeholders.
  4. Perform a lessons learned.

Answer(s): C

Explanation:

The newly appointed project manager should identify stakeholders next. Understanding who the stakeholders are, their interests, and their influence on the project is crucial for planning and managing the project effectively.
Stakeholder identification allows the project manager to tailor communication and ensure that the right people are engaged throughout the project lifecycle.



A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?

  1. Pareto
  2. Scatter
  3. Network
  4. Fishbone

Answer(s): A

Explanation:

The Pareto diagram, also known as the
rule, is based on the principle that 80% of problems or issues are caused by 20% of the causes. It helps prioritize issues by visually showing which causes are contributing most to the problems, allowing project teams to focus on the most significant causes to make improvements.



Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

  1. Send the file through email as an attachment.
  2. Share access to the file on a wiki knowledge base.
  3. Access the file through an online application.
  4. Schedule an in-person meeting to review the plan.

Answer(s): C

Explanation:

Using an online application to access and edit the project plan in real time is the best alternative. Tools like Google Sheets, Microsoft Excel Online, or project management software like Trello or Asana allow multiple users to simultaneously view and edit the project plan, ensuring collaboration without version control issues or delays.



A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

  1. Key stakeholder identification
  2. Preliminary procurement
  3. Solution design determination
  4. Critical factor enlistment

Answer(s): B

Explanation:

Preliminary procurement refers to the early stages of the procurement process, where the project manager or
organization outlines the necessary skills, qualifications, and requirements for potential vendors. In this case, the car manufacturer is presenting the qualifications and skills required for the vendors to develop a module of the data warehouse application, which fits the description of preliminary procurement. This is the stage where the organization defines what it needs from the vendors before formally requesting proposals or initiating contracts.



Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

  1. Risk
  2. Change
  3. Defect
  4. Issue

Answer(s): A

Explanation:

The project manager should use the Risk log to capture concerns about potentially losing team members due to a stressful work environment. The Risk log is used to document potential issues that may occur in the future, such as the risk of losing team members, and outline strategies for mitigating or managing those risks.



An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

  1. Development
  2. Production
  3. Testing
  4. QA

Answer(s): B

Explanation:

The Production environment is where the application is live and used by clients. It is the environment where the final version of the application runs, providing services to end-users. Since the application is highly utilized by clients, it is in the production environment.



A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

  1. Assign a scribe to take notes.
  2. Record the meeting and transcribe the notes later.
  3. Instruct each team member to take notes.
  4. Get a facilitator for the meetings.

Answer(s): A

Explanation:

To be more efficient, the project manager should assign a scribe to take notes during the meeting. This allows
the project manager to focus on facilitating the meeting and managing the discussions while ensuring that detailed meeting notes are captured accurately. The scribe can then prepare the meeting minutes for distribution afterward.



A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

  1. Build
  2. Subscription
  3. Lease
  4. Buy

Answer(s): B

Explanation:

A Subscription procurement method would allow the project manager to maximize cost savings in this scenario. With subscription-based software, the project manager can avoid upfront costs and instead pay based on the number of users or usage over time. This method offers flexibility, especially when the exact number of users is unknown, as the costs can scale with the actual usage, preventing overpayment for unused licenses.