By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project.
Which of the following activities still needs to be performed to complete the schedule?

  1. Allocate resources.
  2. Determine the project budget
  3. Develop a communication plan.
  4. Establish baselines.

Answer(s): D



A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks.
Which of the following should be used to document this information?

  1. RFI
  2. RACI
  3. WBS
  4. SOW

Answer(s): B



During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer.
Which of the following documents would the project manager need in order to find this information?

  1. SLA
  2. TOR
  3. SOW
  4. NDA

Answer(s): C



Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

  1. Approving the change request
  2. Developing a rollback plan
  3. Gathering necessary resources
  4. Defining requirements

Answer(s): B



During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity.
Which of the following tools will the project manager MOST likely use?

  1. Issue log
  2. Defect log
  3. Change log
  4. Task board

Answer(s): B