Suppose you are a Scrum Master or a Scrum Team that is progressing through Tuckman's model of Group
Dynamics. In which of the following stages will you be most actively involved?

  1. Forming
  2. Storming
  3. Norming
  4. Performing

Answer(s): A


Reference:

https://project-management.com/the-five-stages-of-project-team-development/



The Scrum Master can help the Product Owner update business justification in the Project Vision statement and ensure continuous value justification for projects by facilitating which of the following processes? A) Conduct Daily Standup
B) Groom Prioritized Product Backlog
C) Retrospect Project
D) Sprint Deliverables

  1. B and D
  2. A and
  3. , B, and
  4. Only

Answer(s): A


Reference:

http://blog.scrumstudy.com/business-justification-in-scrum-2/



While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must consider the primary factors on which the Prioritized Product Backlog is based-on.
Which of the following are those primary factors?
A) Value
B) Dependencies
C) Risk
D) Deliverables

  1. A, , and
  2. A
  3. A, C, and D

Answer(s): A

Explanation:

:
The Prioritized Product Backlog contains a prioritized list of business and project requirements written in the form of Epic(s), which are high level User Stories. The Prioritized Product Backlog is based on three primary factors: value, risk or uncertainty, and dependencies. It is also referred to as the Risk Adjusted Product
Backlog since it includes identified and assessed risks related to the project.


Reference:

http://blog.scrumstudy.com/prioritized-product-backlog-the-backbone-of-a-scrum- project/



You are the Scrum Master for a team that is working on a project for a chemical engineering company. During one of the Sprints, the Product Owner suggests changes to the Acceptance Criteria on the basis of new requirements by the stakeholders.
Which of the following best describes the steps that should be taken next in this situation?

  1. You will direct the Scrum team to re-work the User Story in the same Sprint.
  2. The Scrum Team will not re-work an already developed deliverable; however, the Product Owner will reject the deliverable in Demonstrate and Validate Sprint.
  3. The deliverable is rejected on the basis of the changed requirements, and added to the Prioritized Product
    Backlog with the new Acceptance Criteria to be worked on in a subsequent Sprint.
  4. You should inform the Product Owner that the Scrum Team does not have the bandwidth to re- work the already created deliverable.

Answer(s): C