Between traditional Project Management and Scrum, differences exist in how quality is achieved and/or implemented. In this respect, which of the following is NOT true?

  1. In traditional project management, once the user clarifies their quality expectations, it is the Project
    Manager who defines those user expectations in measurable terms.
  2. In traditional project management, changes can be made only through a formal change management system.
  3. In Scrum, the Scrum Master and the Scrum Team collaborate and decide on the Acceptance Criteria for the User Stories.
  4. In Scrum, the development of the product is carried out by the Scrum Team in short iterations called
    Sprints.

Answer(s): C


Reference:

https://www.scrum.org/index.php/forum/scrum-forum/29049/product-owners-define- acceptancecriteria-
then-refuse-it



During a Scrum of Scrums, each Scrum Team representative provides an update on which of the following:
A) What has my team been working on since the last meeting? B) What will my team do until the next meeting?
C) How many story points has my team completed since the last meeting? D) What is our team planning on doing that might affect other teams?

  1. A, , and
  2. A, C, and D
  3. A, , and D
  4. , C, and D

Answer(s): A


Reference:

http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf (59)



Who among the following can directly approve changes recommended in the project?

  1. Product Owner
  2. Scrum Guidance Body
  3. Scrum Master
  4. Senior Management

Answer(s): B

Explanation:

:

The Scrum Guidance Body usually defines a process for approving and managing changes throughout the organization. In the absence of a formal process, it is recommended that small changes that do not have a significant impact on the project be directly approved by the Product Owner. The tolerance for such small changes could be defined at an organizational level or by the sponsor for a particular project. In most projects,
90% of Change Requests could be classified as small changes that should be approved by the Product Owner. So, the Product Owner plays a very important role in managing changes in a Scrum Project.


Reference:

http://blog.scrumstudy.com/how-to-handle-request-for-change-or-change-requests-in-a- scrumproject-
2/



During a Scrum of Scrums Meeting certain
During a Scrum of Scrums, each Scrum Team representative provides an update on which of the following:
A) What has my team been working on since the last meeting? B) What will my team do until the next meeting?
C) How many story points has my team completed since the last meeting? D) What is our team planning on doing that might affect other teams?

  1. A, , and
  2. A, C, and D
  3. A, , and D
  4. , C, and D

Answer(s): A



A) What has my team been working on since the last meeting? B) What will my team do until the next meeting?
C) What were other teams counting on our team to finish that remains undone? D) What is our team planning on doing that might affect other teams?

  1. C and D
  2. A and
  3. , B, and D
  4. All of the above.

Answer(s): C

Explanation:


Reference:

http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf (59)



Viewing page 17 of 47
Viewing questions 81 - 85 out of 230 questions


Post your Comments and Discuss EXIN ASM exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!