Whose approval may be required for change requests after change control board (CCB) approval?

  1. Functional managers
  2. Business partners
  3. Customers or sponsors
  4. Subject matter experts

Answer(s): C



The primary benefit of the Plan Schedule Management process is that it:

  1. provides guidance to identify time or schedule challenges within the project.
  2. tightly links processes to create a seamless project schedule.
  3. guides how the project schedule will be managed throughout the project.
  4. creates an overview of all activities broken down into manageable subsections.

Answer(s): C



Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

  1. Influence/impact grid
  2. Power/influence grid
  3. Power/interest grid
  4. Salience model

Answer(s): C



Variance and trend analysis is a tool and technique used in which process?

  1. Perform Qualitative Risk Analysis
  2. Perform Quantitative Risk Analysis
  3. Control Risks
  4. Plan Risk Responses

Answer(s): C



An intentional activity to modify a nonconforming product or product component is called:

  1. defect repair
  2. work repair
  3. corrective action
  4. preventive action

Answer(s): A