Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

  1. Smooth/accommodate
  2. Withdraw/avoid
  3. Compromise/reconcile
  4. Force/direct

Answer(s): B



At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project.
Which item did this project create?

  1. Result
  2. Product
  3. Service
  4. Improvement

Answer(s): A



Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

  1. Cause-and-effect diagram
  2. Histogram
  3. Control chart
  4. Scatter diagram

Answer(s): D



Which item is a cost of conformance?

  1. Training
  2. Liabilities
  3. Lost business
  4. Scrap

Answer(s): A



Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  1. Estimate Costs
  2. Control Costs
  3. Plan Cost Management
  4. Determine Budget

Answer(s): D