A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

  1. Cost Plus Incentive Fee (CPIF).
  2. Fixed Price Incentive Fee (FPIF).
  3. Cost Plus Award Fee (CPAF).
  4. Fixed Price with Economic Price Adjustment (FP-EPA).

Answer(s): B



Which enterprise environmental factors may influence Plan Schedule Management?

  1. Cultural views regarding time schedules and professional and ethical behaviors
  2. Historical information and change control procedures
  3. Risk control procedures and the probability and impact matrix
  4. Resource availability and organizational culture and structure

Answer(s): D



Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

  1. Internal
  2. External
  3. Discretionary
  4. Mandatory

Answer(s): C



When the business objectives of an organization change, project goals need to be:

  1. realigned.
  2. performed.
  3. improved.
  4. controlled.

Answer(s): A



Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

  1. Activity network diagrams
  2. Affinity diagrams
  3. Matrix diagrams
  4. Interrelationship digraphs

Answer(s): B