Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

  1. Critical path method
  2. Critical chain method
  3. Resource leveling
  4. Schedule network analysis

Answer(s): B



The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

  1. work package
  2. deliverable
  3. milestone
  4. activity

Answer(s): A



The scope management plan and scope baseline are contained in:

  1. organizational process assets
  2. a requirements traceability matrix
  3. the project charter
  4. the project management plan

Answer(s): D



Which Manage Communications tool or technique focuses on identifying and managing barriers?

  1. Communication methods
  2. Information technology
  3. Communication models
  4. Information management systems

Answer(s): C