A project manager who communicates to the project team though email is using which type of communication?

  1. Formal
  2. Informal r
  3. Horizontal
  4. Unofficial

Answer(s): B



An input to the Perform Integrated Change Control process is:

  1. expert judgment
  2. seller proposals
  3. the project charter
  4. the project management plan

Answer(s): D



Which tool or technique is required in order to determine the project budget?

  1. Cost of quality
  2. Historical relationships
  3. Project management software
  4. Forecasting

Answer(s): B



Requirements documentation will typically contain at least:

  1. Stakeholder requirements, staffing requirements, and transition requirements.
  2. Business requirements, the stakeholder register, and functional requirements.
  3. Stakeholder impact, budget requirements, and communications requirements.
  4. Business objectives, stakeholder impact, and functional requirements.

Answer(s): D



Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

  1. Define Activities
  2. Direct and Manage Project Work
  3. Develop Project Management Plan
  4. Develop Project Charter

Answer(s): D

Explanation: