The stakeholder register is an output of:

  1. Identify Stakeholders.
  2. Plan Stakeholder Management.
  3. Control Stakeholder Engagement.
  4. Manage Stakeholder Engagement.

Answer(s): A



An output of the Develop Project Team process is:

  1. change requests
  2. team performance assessments
  3. project staff assignments
  4. project documents updates

Answer(s): B



Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

  1. Portfolio
  2. Project
  3. Program
  4. Operations

Answer(s): D



Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

  1. Program
  2. Functional
  3. Project
  4. Portfolio

Answer(s): C



The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

  1. Methodology
  2. Risk category
  3. Risk attitude
  4. Assumption analysis

Answer(s): A