Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

  1. Collect Requirements
  2. Direct and Manage Project Execution
  3. Monitor and Control Project Work
  4. Develop Project Management Plan

Answer(s): D



Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

  1. Initiating
  2. Monitoring and Controlling
  3. Planning
  4. Closing

Answer(s): C



A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.

What is the cost variance?

  1. -700
  2. -200
  3. 200
  4. 500

Answer(s): A



Which type of managers do composite organizations involve?

  1. Functional managers and manager of project managers
  2. Functional managers only
  3. Project managers only
  4. Technical managers and project managers

Answer(s): A



Assigned risk ratings are based upon:

  1. Root cause analysis.
  2. Risk probability and impact assessment.
  3. Expert judgment.
  4. Revised stakeholders' tolerances.

Answer(s): B