Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

  1. Critical path method
  2. Variance analysis
  3. Schedule compression
  4. Schedule comparison bar charts

Answer(s): A



Perform Quality Control is accomplished by:

  1. Identifying quality standards that are relevant to the project and determining how to satisfy them.
  2. Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.
  3. Ensuring that the entire project team has been adequately trained in quality assurance processes.
  4. Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Answer(s): B



Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

  1. Bottom-up
  2. Three-point
  3. Parametric
  4. Analogous

Answer(s): C



Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

  1. Control Schedule
  2. Define Activities
  3. Develop Schedule
  4. Estimate Activity Resources

Answer(s): D



Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

  1. The influence of the stakeholders increases, the cost of changes increases.
  2. The influence of the stakeholders decreases, the cost of changes increases.
  3. The influence of the stakeholders increases, the cost of changes decreases.
  4. The influence of the stakeholders decreases, the cost of changes decreases.

Answer(s): B