At which point of the project is the uncertainty the highest and the risk of failing the greatest?

  1. Final phase of the project
  2. Start of the project
  3. End of the project
  4. Midpoint of the project

Answer(s): B



What type of project structure is a hierarchically organized depiction of the resources by type?

  1. Organizational breakdown structure (OBS)
  2. Resource breakdown structure (RBS)
  3. Work breakdown structure (WBS)
  4. Project breakdown structure (PBS)

Answer(s): B



When can pre-assignment of project team members occur?

  1. When the project uses capital expenditures
  2. When the required staff can be acquired from outside sources
  3. When the project would be ignored due to travel expenses
  4. When the project is the result of specific people being promised as part of a competitive proposal

Answer(s): D



An output of the Create WBS process is:

  1. Scope baseline.
  2. Project scope statement.
  3. Organizational process assets.
  4. Requirements traceability matrix.

Answer(s): A



Change requests are an output from which Project Integration Management process?

  1. Direct and Manage Project Execution
  2. Develop Project Management Plan
  3. Close Project
  4. Develop Project Charter

Answer(s): A