What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

  1. Decomposition
  2. Benchmarking
  3. Inspection
  4. Checklist analysis

Answer(s): C



To which process is work performance information an input?

  1. Administer Procurements
  2. Direct and Manage Project Execution
  3. Create WBS
  4. Perform Qualitative Risk Analysis

Answer(s): A



Which defines the portion of work included in a contract for items being purchased or acquired?

  1. Procurement management plan
  2. Evaluation criteria
  3. Work breakdown structure
  4. Procurement statement of work

Answer(s): D



Cost baseline is an output of which of the following processes?

  1. Control Costs
  2. Determine Budget
  3. Estimate Costs
  4. Estimate Activity Resources

Answer(s): B



Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

  1. The Delphi technique
  2. Nominal group technique
  3. Affinity diagram
  4. Brainstorming

Answer(s): A