Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

  1. influencing
  2. leadership
  3. motivation
  4. coaching

Answer(s): A



Those who enter into a contractual agreement to provide services necessary for a project are:

  1. buyers
  2. sellers
  3. business partners
  4. product users

Answer(s): B



A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

  1. cultural differences of team members
  2. possibility of communication misunderstandings
  3. costs associated with travel
  4. costs associated with technology

Answer(s): C



A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

  1. risk management plan
  2. human resource management plan
  3. scope management plan
  4. procurement management plan

Answer(s): D



In the Define Activities process, the schedule management plan is used to:

  1. Capture the lessons learned from other projects for comparison.
  2. Contain the standard activity list.
  3. Document and support the project change requests.
  4. Prescribe the level of detail needed to manage the work.

Answer(s): D