GAQM APM-001 Exam Questions
Associate in Project Management (APM) (Page 7 )

Updated On: 12-Apr-2026

An example of a group decision-making technique is:

  1. nominal group technique
  2. majority
  3. affinity diagram
  4. multi-criteria decision analysis

Answer(s): B



Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

  1. Procurement documents
  2. Inspection and audits
  3. Estimate budget
  4. Risk register

Answer(s): B



Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

  1. Influencing
  2. Motivation
  3. Negotiation
  4. Trust building

Answer(s): B



The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?

  1. 10
  2. 12
  3. 14
  4. 16

Answer(s): A



The following is a network diagram for a project.



The critical path for the project is how many days in duration?

  1. 10
  2. 12
  3. 14
  4. 17

Answer(s): D



Viewing page 7 of 112
Viewing questions 31 - 35 out of 704 questions



Post your Comments and Discuss GAQM APM-001 exam dumps with other Community members:

APM-001 Exam Discussions & Posts

AI Tutor AI Tutor 👋 I’m here to help!