A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

  1. Work breakdown structure
  2. Requirements document
  3. Project charter
  4. Project management plan

Answer(s): C



Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

  1. Schedule network analysis
  2. Reserve analysis
  3. Alternative analysis
  4. Variance analysis

Answer(s): D



Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

  1. Decomposition
  2. Inspection
  3. Project analysis
  4. Document analysis

Answer(s): A



One of the key benefits of the Plan Human Resource Management process is that it:

  1. outlines team selection guidelines and team member responsibilities.
  2. establishes project roles and responsibilities.
  3. improves teamwork, interpersonal skills, and competencies.
  4. provides an accurate appraisal of team member performance.

Answer(s): B



The following chart contains information about the tasks in a project.



Based on the chart, what is the schedule performance index (5PI) for Task 4?

  1. 0.83
  2. 0.9
  3. 1.11
  4. 1.33

Answer(s): C