Free APM-001 Exam Braindumps (page: 7)

Page 6 of 139

Which tools or techniques are used during the Close Project or Phase process?

  1. Reserve analysis and expert judgment
  2. Facilitation techniques and meetings
  3. Expert judgment and analytical techniques
  4. Performance reviews and meetings

Answer(s): C



When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

  1. improvement
  2. program
  3. result
  4. portfolio

Answer(s): A



The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

  1. management
  2. response
  3. tolerance
  4. appetite

Answer(s): D



The zero duration of milestones in project planning occurs because milestones:

  1. Are unpredictable and challenge the Plan Schedule Management process.
  2. Occur at random times in the project plans.
  3. Represent a moment in time such as a significant project point or event.
  4. Represent both significant and insignificant points in the project and are difficult to anticipate.

Answer(s): C






Post your Comments and Discuss GAQM APM-001 exam with other Community members:

APM-001 Discussions & Posts