Failure costs are also known as which of the following?

  1. Internal costs
  2. Prevention costs
  3. Cost of keeping defects out of the hands of customers
  4. Cost of poor quality

Answer(s): D

Explanation:

Failure costs are associated with the cost of quality and are also known as cost of poor quality.



During the opening rounds of contract negotiation, the other party uses a fait accompli tactic.
Which of the following statements is true about fait accompli tactics?

  1. One party claims the issue under discussion was documented and accepted as part of Scope Verification.
  2. One party claims the issue under discussion has already been decided and can't be changed.
  3. One party claims to accept the offer of the other party, provided a contract change request is submitted describing the offer in detail.
  4. One party agrees to accept the offer of the other party but secretly knows they will bring the issue back up at a later time.

Answer(s): B

Explanation:

Fait accompli is a tactic used during contract negotiations where one party convinces the other that the particular issue is no longer relevant or cannot be changed. Option B is not correct because Scope Verification does not generally occur during contract negotiations since the work of the project has not yet been performed.



The most rapid Estimate Costs technique is:

  1. Analogous estimating
  2. Template estimating
  3. Computerized estimating
  4. Square foot estimating

Answer(s): C

Explanation:

Computerized estimating rapid Estimate Costs technique



Management styles associated with production environments, such as assembly lines commonly include:

  1. assumption that workers lack ambition and dislike responsibility
  2. All of the other alternatives apply.
  3. a directing style of leadership.
  4. a lack of confidence in their workers
  5. a Theory X style of leadership

Answer(s): B



The person in the organization that authorizes the commencement of a project is the
______________?

  1. Project Admin
  2. Sponsor
  3. Project Manager
  4. Senior Manager

Answer(s): B

Explanation:

The project manager executes the project but does not authorize the project. Sponsor authorize the project.