You have accumulated project information throughout the project and need to distribute some important information you just received.
Which of the following is not an information distribution method?

  1. Electronic mail
  2. Videoconferencing
  3. Voicemail
  4. Electronic databases

Answer(s): D

Explanation:

Electronic databases are a type of information gathering and retrieval system, not a distribution method.



The following reports are normally developed during the project closure phase?

  1. None of the other alternatives apply
  2. Communications Management Plan and Lessons Learned
  3. Records Archive, Closure Report, & Specifications Document
  4. Records Archive, Closure Report, lessons learned & Formal Acceptance Report
  5. Communications Management Plan and Closure report

Answer(s): D



Which one of the following is not an acquisition method?

  1. negotiation
  2. invitation
  3. purchase
  4. advertising
  5. all are acquisition methods

Answer(s): D



Communication in both project and non-project-driven organizations should occur in directions.

  1. four
  2. one
  3. two
  4. three
  5. five

Answer(s): E



In which of the following is the cost of risk hidden by the contractor?

  1. Fixed Price Plus Incentive
  2. Firm Fixed Price Contract and Fixed Price Plus Incentive
  3. Firm Fixed Price Contract
  4. Cost Plus Percentage of Cost
  5. Cost Plus Fixed Price

Answer(s): D