Which of the following statements is true regarding schedule variances?
Answer(s): B
Schedule variances will sometimes-but not always-impact the schedule. Changes to non- critical path tasks will not likely impact the schedule, but changes to critical path tasks will always impact the schedule.
Which is not an example of formal communication?
Communication via email is not considered a formal communication.
You know that PV = 470, AC = 430, EV = 480, EAC = 500, and BAC = 525. What is VAC?
Answer(s): A
VAC is calculated this way: VAC = BAC - EAC. Therefore, 525 - 500 = 25.
In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
Bar charts are most appropriate for: