The Delphi Method is well-suited for:

  1. Decision-making
  2. All of the other alternatives apply
  3. Decision-making and Forecasting
  4. Forecasting
  5. Overhead rate estimating

Answer(s): C



A non-critical path activity is completed in half the time. Then,

  1. All of the other alternatives apply.
  2. The slack in the path containing this activity will increase.
  3. The total cost for this activity has decreased.
  4. The critical path is also reduced.
  5. Manpower from this activity can be assigned to other activities.

Answer(s): B



Advantages of the functional (hierarchical) form of organization include _____ and creation of technical competence.

  1. Single voice to customers
  2. High information processing capability
  3. Ease of horizontal coordination
  4. Clearly defined authority

Answer(s): D



During your project meeting, a problem was discussed, and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received an email from one of the meeting participants saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is a result of which of the following conflict resolution techniques?

  1. Forcing
  2. Confrontation
  3. Storming
  4. Smoothing

Answer(s): D

Explanation:

The smoothing technique does not usually result in a permanent solution. The problem is downplayed to make it seem less important than it is, which makes the problem tend to resurface later.



Which of the following would most likely increase the accuracy of estimating the project cost?

  1. Using historical data.
  2. Pricing out the work at lower levels in the work breakdown structure.
  3. Both 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects.
  4. Talking to people who have worked on similar projects.
  5. 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects, and 3) Using historical data.

Answer(s): E