You are a project manager of Software Product Company. After hired a person you got to know that many of this person's ideas were developed by the competing company. Are you going to implement the same ideas?

  1. Accept the new ideas.
  2. Ask to sign NDA.
  3. Ignore the ideas because it may be violation of code of conduct.
  4. Tell the person that he should not mention that the ideas came from another company.

Answer(s): A

Explanation:

Unless the employee signed the NDA with his or her previous organization, there is no obligation for him or her not to share knowledge that was gained while working for the competitor.



Risk Event Status is defined as _____ .

  1. Both 1) the severity of the consequences, and 2)how likely the event is to occur with risk.
  2. (Cost + Benefit + Business Risk) / Insurable Risk.
  3. how likely the event is to occur with risk.
  4. Risk Probability x Amount At Stake.
  5. the severity of the consequences.

Answer(s): D



Which statement is TRUE about Present Value(PV)?

  1. The difference in benefit received between a chosen project and a project that was not chosen
  2. The interest rate that makes the net present value of all cash flow equal zero
  3. The value today of future cash flow
  4. The present value of cash inflow less the present value of cash outflow

Answer(s): C

Explanation:

Present Value(PV): The value today of future cash flow. The higher the PV, the better.



All of the following are tools and techniques of the Performance Reporting process except which one?

  1. Performance measurements
  2. Information presentation tools
  3. Time reporting systems
  4. Cost reporting systems

Answer(s): A

Explanation:

The tools and techniques of the Performance Reporting process are information presentation tools, performance information gathering and compilation, status review meetings, time reporting systems, and cost reporting systems.



Most project (and non-project) managers prefer _____ communications.

  1. Lateral
  2. Oral
  3. Downward
  4. Written
  5. Upward

Answer(s): B



Viewing page 55 of 131
Viewing questions 271 - 275 out of 650 questions