A computer tape which contains historical project information is called ____ tape.

  1. Database
  2. Archive.
  3. Lessons learned.
  4. Baseline.
  5. Life cycle summary.

Answer(s): B



Power games, withholding information, and hidden agendas are examples of-.

  1. mixed messages
  2. indirect communication
  3. noise
  4. communication barriers
  5. All of the other alternatives apply

Answer(s): D



Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues.
Which of the following should you consider?

  1. Training
  2. Co-location
  3. Corrective action
  4. Conflict resolution

Answer(s): B

Explanation:

Co-location would bring your team members together in the same location and allow them to function more efficiently as a team. At a minimum, team members meeting in a common room, such as a war room, for all team meetings would bring the team closer together.



Risk event is the description of what may happen to the _____ of the project.

  1. Budget
  2. harm
  3. Schedule
  4. Manager

Answer(s): B

Explanation:

Risk event is the description of what may happen to the harm of the project.



Which of the following is NOT part of stakeholder's management?

  1. Identify stakeholder's need
  2. make sure all the stakeholders are in project plan
  3. Identify stakeholders
  4. make sure all the stakeholders are in communication plan

Answer(s): B

Explanation:

Stakeholders are NOT in project plan.