A project manager is assigned to a project which phase of the project?

  1. Closing
  2. Initiation
  3. Estimation
  4. Planning

Answer(s): B

Explanation:

In the Initiation phase, the sponsor releases resources to get the project done, and the project manager is chosen.



Which describes how cost variances will be managed?

  1. Cost management plan
  2. Cost baseline
  3. Cost estimate
  4. Chart of accounts

Answer(s): A

Explanation:

Cost management plan describes how cost variances will be managed.



History has shown that project managers can be trained in a combination of ways.
Which method is usually preferred by most companies?

  1. None of the other alternatives apply
  2. Formal education and special course (degreed programs)
  3. Experiential learning, on-the-job
  4. Professional activities, seminars
  5. Individual readings

Answer(s): C



Who is responsible for decide project management process for a particular project?

  1. Sponsor
  2. Project Manager
  3. Stakeholders
  4. Senior management

Answer(s): B

Explanation:

Project Manager is responsible for decide project management process for a particular project.



The most common form of written project communication is

  1. Bulletin boards
  2. All of the other alternatives apply
  3. Publications
  4. Letters and memos
  5. Reports

Answer(s): D