How is quality control performed?

  1. By identifying quality standards that are relevant to the project and determining how to satisfy them.
  2. By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed.
  3. By ensuring that the entire project team has been adequately trained in quality assurance processes.
  4. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance to quality standards.

Answer(s): B



As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?

  1. BAC
  2. EAC
  3. ETC
  4. WBS

Answer(s): B



How is scheduled variance calculated using the earned value technique?

  1. EV less AC
  2. AC less PV
  3. EV less PV
  4. AC less EV

Answer(s): C



The project management processes presented in the PMBOK Guide should:

  1. Always be applied uniformly
  2. Be selected as appropriate by the sponsor
  3. Be selected as appropriate by the project team
  4. Be applied based on ISO guidelines.

Answer(s): C



Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

  1. Project sponsor and project manager
  2. Project sponsor and functional manager
  3. Project manager and project team
  4. Project team and functional manager

Answer(s): C

Explanation:

The project management processes are presented as discrete elements with well- defined interfaces. However, in practice they overlap and interact in ways that are not completely detailed here. Most experienced project management practitioners recognize there is more than one way to manage a project. The specifics for a project are defined as objectives that must be accomplished based on complexity, risk, size, time frame, project team's experience, access to resources, amount of historical information, the organization's project management maturity, and industry and application area. The required Process Groups and their constituent processes are guides to apply appropriate project management knowledge and skills during the project. In addition, the application of the project management processes to a project is iterative and many processes are repeated and revised during the project. The project manager and the project team are responsible for determining what processes from the Process Groups will be employed, by whom, and the degree of rigor that will be applied to the execution of those processes to achieve the desired project objective.



Viewing page 65 of 131
Viewing questions 321 - 325 out of 650 questions


Post your Comments and Discuss GAQM PPM-001 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!