Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

  1. Perform Quality Control
  2. Quality Policy
  3. Perform Quality Assurance
  4. Quality Planning

Answer(s): C



Which process occurs within the Monitoring and Controlling Process Group?

  1. Cost Control
  2. Quality Planning
  3. Quantitative Risk Analysis
  4. Cost Budgeting

Answer(s): A



The Define Scope process is in which of the following process groups?

  1. Initiating
  2. Planning
  3. Monitoring & Controlling
  4. Executing

Answer(s): B



Which activity is an input to the select sellers process?

  1. Organizational process assets
  2. Resource availability
  3. Change control process
  4. Team performance assessment

Answer(s): A



What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

  1. Pareto
  2. Ishikawa
  3. Shewart-Deming
  4. Delphi

Answer(s): C