You are documenting the requirements attribute for your requirements management plan.
Which attribute would you use if you want to identify the person who created the requirements?

  1. Absolute reference
  2. Ownership
  3. Requirements sponsor
  4. Author of the requirements

Answer(s): D

Explanation:

The author of the requirements is a good attribute to include in the requirements attribute. This allows follow- up Questions or clarifications, if necessary, for the project. Answer A is incorrect. Absolute reference is needed to define specific requirements. A numeric coding is preferred over text and this code should not be reused. Answer B is incorrect. The ownership attribute describes who will be the owner of the requirement or deliverable. The owner isn't necessarily the same person who created the requirement. Answer C is incorrect. There is not an attribute called requirements sponsor, so this choice is not valid.



A business analyst has just completed an elicitation event.
What stakeholder(s) is/are involved in the documentation of the elicitation results?

  1. Business analyst and key stakeholders
  2. Business analyst
  3. Project manager, project team, and business analyst
  4. Project manager, business analyst, and project sponsor

Answer(s): B

Explanation:

Only the business analyst is involved in the documentation of the elicitation results. Answer D is incorrect. Only the business analyst is involved in the documentation of the elicitation results, not the project manager and project sponsor.
Answer C is incorrect. Only the business analyst is involved in the documentation of the elicitation results, not the project manager and project team.
Answer A is incorrect. Only the business analyst is involved in the documentation of the elicitation results, not key stakeholders.



Consider a business analyst who is completing the business analysis tasks of specifying and modeling requirements for an organization. This task can help an organization achieve all of the following objectives except for which one?

  1. Supporting training activities and knowledge management
  2. Facilitating communication among stakeholders
  3. Compliance with contracts and regulations
  4. Increasing revenue and/or reducing costs within an organization

Answer(s): D

Explanation:

The task of specifying and modeling requirements does not ensure that revenues will increase or that costs will be reduced. However, the task does allow for some insight into operational improvements. Answer C is incorrect. The task of specifying and modeling requirements does help with compliance to contracts and regulations.

Answer B is incorrect. The task of specifying and modeling requirements does help the stakeholders communicate better.
Answer A is incorrect. The task of specifying and modeling requirements can help with training and knowledge management.



In order to begin defining the solution scope, you'll need four inputs.
Which one of the following is actually a task that will use the solution scope and is not an input?

  1. Required capability
  2. Assumptions and constraints
  3. Business need
  4. Allocation of requirements

Answer(s): D

Explanation:

The task of allocating requirements is the future task in the business analysis domain that will need the solution scope. The four inputs to the solution scope are assumptions and constraints, business need, required capabilities, and solution approach.
Answer B is incorrect. Assumptions and constraints is one of the four inputs to the solution scope.

Answer C is incorrect. Business need is one of the four inputs to the solution scope. Answer A is incorrect. Required capability is one of the four inputs to the solution scope.



Page 19 of 129



Post your Comments and Discuss IIBA CCBA exam with other Community members:

Mohammed Basheer commented on August 23, 2017
Wrote the exam today and I passed it easily. Valid dump!
UNITED STATES
upvote