Tracy is a business analyst for her organization and she's gathered and identified the needed requirements for the solution scope.
What must Tracy do before she can begin managing the requirements? Choose the best answer.

  1. Tracy must decompose the requirements in WBS.
  2. Tracy must create cost-benefits analysis of each requirement to manage the benefits first.
  3. Tracy must identify roles, responsibilities, and owners of the requirements to fully manage the requirements.
  4. Tracy must communicate the requirements to the stakeholders for their consent and approval.

Answer(s): D

Explanation:

Requirements must be communicated before they are managed. Tracy must communicate the requirements to the stakeholders for their consent and approval before managing the requirements. Answer A is incorrect. Before Tracy decomposes the requirements, she should have the approval of the stakeholders.
Answer B is incorrect. To begin managing the requirements, Tracy needs the approval and consent of the stakeholders.
Answer C is incorrect. This isn't a valid statement, as the best thing to do is to gain the approval of the stakeholders first.



Ben is the business analyst for his organization. Ben is currently working on a solution to improve a laser printer. He has taken the laser printer apart, identified each component, and documented each component's purpose.
What type of requirements organization is Ben doing in this scenario?

  1. Functional decomposition
  2. Process modeling
  3. Scope modeling
  4. Data modeling

Answer(s): A

Explanation:

Ben is completing the functional decomposition technique for the organize requirements process. Each component in the printer can have its own set of requirements, while the improved printer to be manufactured is the ultimate goal of the requirements. Answer D is incorrect. Data modeling describes the concepts and relationships relevant to the solution or business domain.

Answer C is incorrect. Scope modeling allows the requirements to be organized by the solution component they're relevant to.
Answer B is incorrect. Process modeling is the activity of representing processes of an enterprise, so that the current process may be analyzed and improved in future. It allows the requirements to be organized around the related processes. Processes are also considered to have sub-processes, inputs, and outputs.



You are the business analyst for your organization and you're working with Fran on business analysis processes. Fran is a stakeholder who wants to ensure that your business analysis approach and activities are compatible with the project activities. Of the following, what type of business analysis stakeholder is Fran?

  1. Regulator
  2. Project manager
  3. Sponsor
  4. Domain subject matter expert

Answer(s): B

Explanation:

Fran is the project manager. The project manager must ensure that the business analysis approach is compatible with other project activities.
Answer D is incorrect. The domain subject matter expert is a person who is steeped in knowledge regarding the project's purpose.
Answer A is incorrect. The regulator approves any tailoring to the business analysis processes or activities. Answer C is incorrect. The sponsor allows the business analysis activities and resources to exist in support of the organization.



You are a business analyst for your organization and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization.
Which of the following statements is true regarding the plan business analysis approach?

  1. The plan business analysis approach describes the amount of budget needed for the requirements elicitation.
  2. The plan business analysis approach is required to select an approach that will perform business analysis.
  3. The plan business analysis approach describes the processes the business analyst will or will not do, based on the time and budget available.
  4. The plan business analysis approach describes the amount of time needed for the business analysis approach.

Answer(s): B

Explanation:

The plan business analysis approach is required to select an approach that will perform business analysis. This approach helps to find out the following:
Which stakeholders need to be involved in the decision? Who will be consulted regarding and informed of the approach? What is the rationale for using it? Answer D, A, and C are incorrect. These statements are not true regarding the plan business analysis approach.



Page 2 of 129



Post your Comments and Discuss IIBA CCBA exam with other Community members:

Mohammed Basheer commented on August 23, 2017
Wrote the exam today and I passed it easily. Valid dump!
UNITED STATES
upvote