Free CCBA Exam Braindumps
Certification of Competency in Business Analysis Questions 131–135 (page: 28)

Updated On: 9-Feb-2026

When can changes to requirements occur in a business analysis planning and monitoring assignment?

  1. Changes to requirements can occur any time after the project's change control system has been enacted.
  2. Changes to requirements can occur at any time.
  3. Change to requirements can occur any time before the project scope statement is created.
  4. Change to requirements can occur at any time before the key stakeholders approve the identified requirements.

Answer(s): B

Explanation:

Changes to requirements can, and often do, happen at any time. Answer D is incorrect. Just because the key stakeholders approve the requirements does not mean that they would not like to add requirements later in the project. Answer C is incorrect. The project scope is generally a good reflection of the identified requirements, but changes can still happen.
Answer A is incorrect. Changes to the requirements can happen even before the project begins.



You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis.
Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?

  1. Requirements-driven approach
  2. Change-driven approach
  3. Plan-driven approach
  4. Value-driven approach

Answer(s): C

Explanation:

The plan-driven approach has the most business analysis work at the beginning of the project or during the start of a project phase. This approach has a high amount of formality and detail for all areas of the business analysis duties, requirements gathering, and monitoring. Answer B is incorrect. Change-driven approach uses short iterations of business analysis tasks throughout the project.
Answer A is incorrect. Requirements-driven approach is not a valid business analysis term. Answer D is incorrect. Value-driven approach is not a valid business analysis term.



Some of the requirements in the solution must be completed because of laws and regulations in your industry.

Management would like you, the business analyst, to rank the requirements according to the relevant laws.
What type of requirements prioritization is management having you complete?

  1. Business value ranking
  2. Risk ranking
  3. Constraint ranking
  4. Regulatory ranking

Answer(s): D

Explanation:

This is an example of a regulatory ranking as you're prioritizing the requirements based on the requirements that must be implemented based on the regulatory demands. Answer B is incorrect. Risk ranking is a prioritization of requirements based on their associated technical risks.
Answer C is incorrect. This is not a valid prioritization method. Answer A is incorrect. The business value ranking prioritizes requirements based on their cost- benefit analysis.



There are three inputs for stakeholder analysis.
Which input describes the existing organizational units and their interactions with one another?

  1. Business need
  2. Enterprise architecture
  3. Matrix structure
  4. Organizational process asset

Answer(s): B

Explanation:

The enterprise architecture describes the relationship among the organizational units and their interactions with one another.
Answer A is incorrect. Business need describes business requirements, solution scope, and solution requirements.
Answer C is incorrect. A matrix structure is not one of the three inputs for stakeholder analysis. Answer D is incorrect. Organizational process assets describe the organizational policies, procedures, forms, and methodologies the business analyst is to follow.



Which of the following defines all of the features and functions of the thing, solution, or service the project or organization will create?

  1. Requirements envisioning
  2. Project scope
  3. Requirements foundation
  4. Product scope

Answer(s): D

Explanation:

Explanation

The product scope defines all of the features and functions of the thing, solution, or service the project or organization will create.

Answer B is incorrect. The project scope defines all of the required work to satisfy the requirements of the project.
Answer A is incorrect. The initial high-level listing of requirements in a change-driven approach is also known as requirements envisioning.
Answer C is incorrect. Requirements foundation is not a valid term for business analysis.



Viewing page 28 of 104
Viewing questions 136 - 140 out of 638 questions


Post your Comments and Discuss IIBA CCBA exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!