DRAG DROPA discrete manufacturer uses the time and attendance registration for production operations.All employees register daily dock in and clock out times during a 40-hour. Monday through Friday workweek.Pay periods are every two weeks. Workers are paid hourly.The production manager will create work schedules with the following windows:Mandatory work hoursWork hours during which employees can leave early without accruing absencesWork hours during which employees can work extra timeIf a junior production worker works over 90 hours in a pay period, the worker will receive time and a half over 80 hours. If a senior production worker works over 90 hours in a pay period, the worker will receive double time over 80 hours.You need to configure the system for these requirements.Where should you configure this functionality? To answer, drag the appropriate forms to the correct requirements. Each form may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.Note: Each correct selection is worth one point.Select and Place:
Answer(s): A
Box 1: Flex groupsFlex groupsFlexible working hours let companies minimize payments for overtime by offering workers extra time off during periods when the workload is low. This feature is relevant, for example, in segments that experience seasonal changes in workload.You can use flex groups to set the following rules and principles for a worker's flexible hours:Rules for flex regulationsPrinciple for calculating the worker's flex balanceBox 2: Calendar working timesA seven-day pattern of hours that are ordinarily worked is called a working time template. After you create a working time template for each schedule that hourly workers in your organization typically work, you can use the template to generate a working time calendar of one year or more. When you specify the working time calendar as the schedule for a position, all workers who are assigned to the position use that schedule. The scheduled hours are used to generate the default earnings statement lines for the worker-position combination.Schedules that are based on working time calendars are also used with leave types for paid leave, for both hourly workers and salaried workers.
https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/time-attendance-flex-groups https://learn.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/work-schedule-and-leave-tasks
DRAG DROPYou are the quality assurance manager of a pharmaceuticals company.One of your customers has requested to only receive batches of item B0001 that have an acid concentration between 5.5 10.5 percent.You need to set up the customer specific batch attribute to track percent acid for B0001.Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.Select and Place:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/batch-attributes
A manufacturer uses Dynamics 365 Supply Chain Management to build bicycles.When manufacturing releases production orders to the warehouse, the warehouse must avoid automatically releasing the bill of materials (BOM) and formula lines. The BOM and formula lines must be manually released later through a batch process.You need to configure the functionality for the records.At which two locations should you configure this functionality? Each correct answer presents a complete solution.Note: Each correct selection is worth one point.
Answer(s): B,C
Note: Methods for releasing BOM and formula linesYou can configure the release of BOM and formula lines so that it occurs as part of the release of a production order or batch order. Alternatively, the release can be controlled by a batch job or done as a manual interaction.The method that is used to release BOM and formula lines is controlled by the Production line release parameter. You can find this parameter at Production control > Setup > Production parameters.* Release BOM and formula lines as part of production or batch order release In this method, BOM and formula lines for a production or batch order are released as part of the process of releasing the order. Usually, during the release of a production or batch order, production jobs are released to the shop floor workers, and production papers are printed. During this process, the status of the order is also changed to Released.* Release BOM and formula lines via a batch job or as a manual interaction In this method, BOM and formula lines can be released only through the Automatic release of BOM and formula lines batch job or as a manual interaction. To manually release BOM and formula lines, on the production order list page or the production order details page, on the Action Pane, select Release to warehouse.Note 2:Unreleased material lines needing attentionA BOM or formula line can be released to the warehouse in three ways:As part of a production order or batch order releaseAs a manual releaseAutomatically through a batch jobIf a BOM or formula line hasn't been released or has been only partly released, and if the date and filter criteria of the workspace are met, the line is included in the calculation of the number that appears on the Unreleased material lines needing attention tile.When you select the tile, the Release to warehouse page is opened. This page shows the number of unreleased BOM and formula lines that is indicated by the number on the tile. The unreleased lines appear in the upper grid. This grid shows the quantity that was originally estimated for the line, the quantity that has already been released, and the remaining quantity that must still be released. You can add lines from the upper grid to the lower grid. From the lower grid, you can then release the selected lines to the warehouse. From the lower grid, you can also adjust the quantity to release so that only a partial quantity is released.
https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/releasing-bom-and-formula- lines-to-warehouse https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/improved-visibility-into- material-exceptions
A company that makes artisan chocolate is implementing Dynamics 365 Supply Chain Management.To safeguard the quality of its ingredients, the company limits recipe substitutions of its chocolates.Its top-selling chocolate bar must contain 20 percent sugar. The sugar can be obtained from either cane or beet sugar depending on supply at the time of production.The system must be able to automatically substitute the appropriate sugar items when generating production orders to meet the quality level of sugar even when the preferred concentration of cane sugar is out of stock.You need to configure the system.Which three components must you configure? Each correct answer presents part of the solution.Note: Each correct selection is worth one point.
Answer(s): A,B,D
A (not F): Formula linesSubstituting material by planningYou can substitute materials during planning only when you're using formulas, not when you're using a BOM.BD: Material substitution by planning is controlled by the Plan group and Priority fields on the formula lines Note: There are three methods for substituting materials during the production process:By date, when one material is substituted for another after a specific date During master planning, when a material in a formula is substituted with a different material, because it's out of stockDuring production, when a material is unexpectedly out of stock and is substituted with a different material
https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/substitute-items-bom-lines
A customer produces light projection toys for holiday decorations throughout the year. The production process creates the projection toy at the following work cells: stands, main assembly, electric, visuals, and packaging.Vendors must create templates for each toy they produce each season. They must manage the transfer of templates to the warehouse. Each transfer for each vendor must use the same purchase agreement.You need to configure the subcontracted transfer activity.What should you do?
Answer(s): C
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity- based-subcontracting#subcontracted-transfer-activities