A company produces generic and name-brand paper plates in the same factory using standard costing and using the same Bill of materials and routes to produce both products.The finance and production teams want a way to view individual raw material consumption costs in the ledger.You need to add a production group to the finished good to control postings to the ledger.What should you do?
Answer(s): B
HOTSPOTA company produces homeopathic lotions for pain relief and uses Dynamics 365 Supply Chain Management.You have been provided the following information for a new relieving lotion.Use the drop-down menus to select the answer choice that completes each statement based on the information presented in the graphic.Note: Each correct selection is worth one point.Hot Area:
Answer(s): A
DRAG DROPA skateboard manufacturer uses route operations to schedule resources and estimate units per hour. All products use the same sub assembly item and resource sanding process.You observe an increase in the number of units a sanding belt resource can produce. The production schedule is now inaccurate due to the number of units the sanding belt line can produce. You must make a permanent change to the number of units the resource can produce for all future orders.You need to adjust the process quantity on the route operation.Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.Select and Place:
DRAG DROPA manufacturing company uses Dynamics 365 Supply Chain Management. The company operates three eight- hour shifts per day, Monday through Friday.The company purchased equipment for a new process that cannot be performed with existing equipment. This specialized equipment performs only this unique task. The machinery must always be monitored and controlled by a worker.The machine must be added to the existing production line and be ready as soon as possible. Future planned production orders must not overload the running maximums of the new machine.You need to configure the system.Which four actions must you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.Select and Place:
Step 1: Add the machine as a resource and set the Finite capacity checkbox to Yes. Future planned production orders must not overload the running maximums of the new machine.Finite capacity Set this option to Yes if the operations resource should be scheduled based on the actual capacity that is available, and if existing capacity reservations should be considered. If this option is set to No, the operations resource is assumed to have infinite capacity, and the resource might therefore be overbooked.Step 2: Create a capability for the machine functions and assign it to the machine. Operations resources perform the activities of a project or a production process. They can be of different types, and can have different capabilities.Step 3: Assign the machine resource to the route operation and approve the route version. A route defines the process for producing a product or product variant. It describes each step (operation) in the production process and the order that these steps must be performed in. For each step, the route also defines the required operations resources, the required setup time and run time, and how the cost should be calculated.Step 4: Assign a working time calendar to the resourceA calendar can be assigned to an operations resource and describes the capacity (in hours) of that resource. The working times of the operations resource are determined by the calendar that is assigned to the resource group that the operations resource is part of.Incorrect:* Add the machine as a resource and set the Exclusive checkbox to Yes. Exclusive Set this option to Yes if you don't want the operations resource to be available for another job or operation until the current production is completed. In this case, the operations resource can't be used even if there are gaps in the resource's run time.* Create a working time templateUse a working time calendar instead.
https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/operations-resources https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/routes-operations
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.A machine in the facility is defective and must be closed for repairs for the next two days.You need to configure the resource calendar to close the resource for production for the next two days.What should you do?