Which role is responsible for creating and communicating the vision for the programme?

  1. Programme office
  2. Business change manager
  3. Programme manager
  4. Senior responsible owner

Answer(s): C


Reference:

https://www.axelos.com/news/blogs/january-2021/msp-vision-statement-programmes- with-purpose



Under which heading in the POTI model should the current performance level of an operational area be recorded?

  1. Process
  2. Organization
  3. Technology
  4. Information

Answer(s): A


Reference:

https://pmtips.net/article/poti-model-programme-blueprints



Which is a feature of an effective programme organization?

  1. Clear accountability for each management role
  2. A business case agreed by the stakeholders
  3. Monitored and controlled programme changes
  4. A quality assured configuration management system

Answer(s): C



Which is a description of a programme resource?

  1. The objective of a programme
  2. A process to control a programme
  3. A logical grouping of projects within a programme
  4. An input required by a programme

Answer(s): D