Which document should be used to provide guidance on the standards that should be followed when producing outputs?

  1. Projects Dossier
  2. Project Brief
  3. Programme Blueprint
  4. Programme Brief

Answer(s): B


Reference:

https://www.simplilearn.com/overview-of-planning-and-control-tutorial



Which risk response encourages collaboration on risk management activities?

  1. Avoid
  2. Reduce
  3. Share
  4. Prepare contingent plans

Answer(s): C


Reference:

https://www.simplilearn.com/overview-of-risk-and-issue-management-tutorial



Which is a characteristic of a programme?

  1. It manages the planning, monitoring and control of projects
  2. It co-ordinates, directs and oversees the implementation of a set of related projects and activities
  3. It delivers one or more outputs in accordance with an agreed business case
  4. It defines an organization's approach to achieving its corporate objectives in a given area of business

Answer(s): B


Reference:

https://repmt.com/learning-paths/msp-managing-successful-programmes/



Which is NOT a purpose of a Blueprint?

  1. Provide a basis for modelling benefits
  2. Provide a usable basis for designing the Projects Dossier
  3. Ensure coherence of the entire future state
  4. Describe how to get to the future state

Answer(s): D


Reference:

https://www.axelos.com/news/blogs/may-2017/the-blueprint-a-cornerstone-of- programmes-and- msp