Which role would be MOST LIKELY to initiate assurance reviews of project performance?

  1. Senior responsible owner
  2. Programme manager
  3. Business change manager
  4. Programme office

Answer(s): B



Which of the following statements about a vision-led programme is true?
1. Tends to be top down in approach, with cross functional implications
2. Evolves from concurrent projects

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 is true

Answer(s): A


Reference:

https://repmt.com/learning-paths/msp-managing-successful-programmes/



What can programme leaders do to influence key stakeholders?

  1. Analyze stakeholder influence and interest
  2. Produce a stakeholder map to show areas of interest
  3. Create a programme communications plan
  4. Hold visioning workshops to draft the vision statement

Answer(s): C



What document provides terms of reference for the Sponsoring Group?

  1. Programme Brief
  2. Quality and Assurance Strategy
  3. Resource Management Plan
  4. Organization Structure

Answer(s): D