When must the change management process be initiated?

  1. When there is a significant change in the scope of the project.
  2. When the customer sends a formal request for additional scope of work.
  3. When the CT head acknowledges that the customer will accept negotiation of the changes in the scope of the contract.
  4. Whenever the project execution requires services or materials different from those agreed in the contractual scope of work.

Answer(s): D



Which of the following inputs are part of the sales to delivery handover?

  1. As sold cost estimate, project plan and PT
  2. Customer PQ, draft of the contract and project schedule.
  3. Cost assumptions, updated country cost database and risk log.
  4. PTA, RFQ and approved cost baseline.

Answer(s): A



During project execution, a large number of changes are made to the project. The project manager should:

  1. wait until all changes are known and print out a new schedule.
  2. make approved changes as needed, but retain the schedule baseline.
  3. make only the changes approved by management.
  4. talk to management before any changes are made.

Answer(s): B



The formula EV - PV provides the:

  1. cost difference.
  2. schedule variance.
  3. schedule difference.
  4. cost variance.

Answer(s): B