What are the key elements that must be monitored constantly over the entire project life cycle?

  1. Quality and subcontractor performance.
  2. Contract conditions and project deliverables.
  3. Cost, time and scope.
  4. Financial reports and schedule.

Answer(s): C



Which are the 3 key players in the sales phase according tothe TRICORN model?

  1. Solution Architect, Project Manager and Care Manager.
  2. Sales Case owner, Customer Solution owner and Project Execution owner.
  3. Sales Case Owner, CT Head and Solution Architect.
  4. Account Manager, Project Manager and Care Manager.

Answer(s): B



Which of these key performance indicators (KPIs) supportsthe identification of possible cost overruns?

  1. Project cost adherence (PCA).
  2. Rollout accuracy (RA).
  3. Site invoice lead time (SILT).
  4. Project asset rotation days (PARD).

Answer(s): A



Which of the following describes earned value:

  1. cost baseline plan.
  2. completed work value.
  3. cost variance.
  4. percentage over or under budget.

Answer(s): B