Why are programme governance baselines updated?

  1. Reflect lessons learned, in Managing the Tranches
  2. Adjust programme governance to align with project governance, in Delivering the Capability
  3. Reflect lessons from earlier programmes, in Identifying a Programme
  4. Prepare for benefit reviews, in Realizing the Benefits

Answer(s): A



What document describes how the roles in the programme team relate to each other?

  1. Stakeholder Profiles
  2. Blueprint
  3. Project Dossier
  4. Organization Structure

Answer(s): D



Which BEST defines something that could have an unfavourable effect on programme objectives?

  1. Risk
  2. Opportunity
  3. Threat
  4. Dis-benefit

Answer(s): C



What role stipulates and guides the direction of a risk actionee?

  1. Risk owner
  2. Design Authority
  3. Programme Manager
  4. Project board

Answer(s): A