Which is a term for the assessment of the management and conduct of a programme?

  1. Benefits modelling
  2. Data measurement
  3. Critical success factors
  4. Programme audit

Answer(s): D



Which is a focus of the Programme Office in managing risks and issues?

  1. Accountable for the management and control of all aspects of the risks assigned to them
  2. Responsible for the implementation of risk response actions
  3. Monitors and reports on business performance issues
  4. Maintains the Risk Register and Issue Register

Answer(s): D



Which is an area of focus of the Programme Office during the design of the Blueprint?

  1. Maintaining control over the different versions of the Blueprint
  2. Consulting with senior business managers on the future state
  3. Providing strategic guidance during the design of the Blueprint
  4. Ensuring a collaborative approach to authoring and assembling the Blueprint

Answer(s): A



What document provides terms of reference for the Sponsoring Group?

  1. Programme Brief
  2. Quality and Assurance Strategy
  3. Resource Management Plan
  4. Organization Structure

Answer(s): D