Free Managing Successful Programme Foundation (MSP) Exam Braindumps (page: 12)

Page 12 of 30

Which is a part of programme planning?

  1. Ensuring the programme manages its projects in detail
  2. Involving widespread discussions to include ambiguities and unknowns
  3. Checking the sustainability of the programme against the Business Case
  4. Providing progress information for benefits reviews

Answer(s): B



What does the ‘I’ stand for in POTI, the model that helps with Blueprint development?

  1. Investment
  2. Implementation
  3. Induction
  4. Information

Answer(s): D



Which communication channel encourages stakeholders to actively take part?

  1. Press release
  2. Intranet home page
  3. Live webcast
  4. Newsletter

Answer(s): C



Which area of management within programme quality tracks and protects project outputs?

  1. Process
  2. Asset
  3. Information
  4. Supply chain

Answer(s): B



Page 12 of 30



Post your Comments and Discuss PEOPLECERT Managing Successful Programme Foundation (MSP) exam with other Community members:

nishant commented on February 01, 2024
Excellent content
Anonymous
upvote