An input to the Plan Cost Management process is:

  1. Cost estimates
  2. Resource calendars
  3. The project charter
  4. The risk register

Answer(s): C

Explanation:

4.1.3.1 Project Charter
The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It documents the business needs, assumptions, constraints, the understanding of the customer’s needs and high-level requirements, and the new product, service, or result that it is intended to satisfy, such as:
Project purpose or justification,
Measurable project objectives and related success criteria, High-level requirements,
Assumptions and constraints,
High-level project description and boundaries, High-level risks,
Summary milestone schedule, Summary budget,

Stakeholder list,
Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project),
Assigned project manager, responsibility, and authority level, and
Name and authority of the sponsor or other person(s) authorizing the project charter.

Process: 7.1 Plan Cost Management
Definition: The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
Key Benefit: The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project.

Inputs
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings

Outputs
Cost management plan



A technique used to determine the cause and degree of difference between baseline and actual performance is:

  1. Product analysis.
  2. Variance analysis.
  3. Document analysis.
  4. Decomposition.

Answer(s): B

Explanation:

5.6.2.1 Variance Analysis
Variance analysis is a technique for determining the cause and degree of difference between the baseline and actual performance. Project performance measurements are used to assess the magnitude of variation from the original scope baseline. Important aspects of project scope control include determining the cause and degree of variance relative to the scope baseline (Section 5.4.3.1) and deciding whether corrective or preventive action is required.



The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

  1. Develop Project Team.
  2. Manage Project Team.
  3. Acquire Project Team.
  4. Plan Human Resource Management.

Answer(s): D

Explanation:

Process: 9.1 Plan Human Resource Management
Definition: The process of identifying and documenting project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan.
Key Benefit: The key benefit of this process is that it establishes project roles and responsibilities, project organization charts, and the staffing management plan including the timetable for staff acquisition and release.

Inputs
1. Project management plan
2. Activity resource requirements
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Organization charts and position descriptions
2. Networking
3. Organizational theory
4. Expert judgment
5. Meetings

Outputs
Human resource management plan



Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

  1. Mandatory
  2. Discretionary
  3. Internal
  4. External

Answer(s): A

Explanation:

6.3.2.2 Dependency Determination
Dependencies may be characterized by the following attributes: mandatory or discretionary, internal or external, as described below. Dependency has four attributes, but two can be applicable at the same time in following ways: mandatory external dependencies, mandatory internal dependencies, discretionary external dependencies, or discretionary internal dependencies.

Mandatory dependencies. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work. Mandatory dependencies often involve physical limitations, such as on a construction project, where it is impossible to erect the superstructure until after the foundation has been built, or on an electronics project, where a prototype has to be built before it can be tested.

Mandatory dependencies are also sometimes referred to as hard logic or hard dependencies. Technical dependencies may not be mandatory. The project team determines which dependencies are mandatory during the process of sequencing the activities. Mandatory dependencies should not be confused with assigning schedule constraints in the scheduling tool.

Discretionary dependencies. Discretionary dependencies are sometimes referred to as preferred logic, preferential logic, or soft logic. Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal. The project team determines which dependencies are discretionary during the process of sequencing the activities.
External dependencies. External dependencies involve a relationship between project activities and non- project activities. These dependencies are usually outside the project team’s control. For example, the testing activity in a software project may be dependent on the delivery of hardware from an external source, or governmental environmental hearings may need to be held before site preparation can begin on a construction project. The project management team determines which dependencies are external during the process of sequencing the activities.
Internal dependencies. Internal dependencies involve a precedence relationship between project activities and are generally inside the project team’s control. For example, if the team cannot test a machine until they assemble it, this is an internal mandatory dependency. The project management team determines which dependencies are internal during the process of sequencing the activities.



Page 4 of 276



Post your Comments and Discuss PMI CAPM exam with other Community members:

Zee commented on September 21, 2024
Are these useful for CAPM exam in 2024?
SOUTH AFRICA
upvote

DonPook commented on August 18, 2024
Is there any difference in downloading the PDF (paying), to the questions provided for free?
Anonymous
upvote

Sharon commented on August 17, 2024
Which exam questions pack can one use inpreparation for the CAPM exam?
Anonymous
upvote

Priyo commented on November 14, 2023
i used this site since 2000, still great to support my career
INDONESIA
upvote

Priyo commented on November 14, 2023
I used this site since 2000, still great to support my career
INDONESIA
upvote

Shayan commented on June 19, 2023
I am here to let you know that about 4 or 5 new questions are added to this exam. I took the exam today and saw those new questions which are not in your exam dumps. I still passed and got 91%.
UNITED STATES
upvote

Roberto commented on May 04, 2021
This is a good hack to pass the exam.
ITALY
upvote

LarBear commented on January 25, 2019
I have used brain dumps before and working great.
UNITED STATES
upvote

Adrian commented on August 11, 2018
The test engine is for windows only so does not work on my mac (I knew this before purchasing as they mention this on the website). The Android app crashes when I try to activate. I purchased from here because of the apps since I can get the pdf questions from several places on the web. Disappointed customer. Try somewhere else.
UNITED STATES
upvote

Life commented on June 22, 2018
Good CAPM questions AND GUIDE!
UNITED STATES
upvote