Free CAPM Exam Braindumps
Certified Associate in Project Management (PMI-100) Questions 546–550 (page: 111)

Updated On: 9-Feb-2026

Which of the following Project Communication Management processes uses performance reports as an input?

  1. Manage Stakeholder Expectations
  2. Report Performance
  3. Distribute Information
  4. Plan Communications

Answer(s): C



Which cost estimate technique includes contingencies to account for cost uncertainty?

  1. Vendor bid analysis
  2. Three-point estimates
  3. Parametric estimating
  4. Reserve analysis

Answer(s): D

Explanation:

6.5.2.6 Reserve Analysis
Duration estimates may include contingency reserves, sometimes referred to as time reserves or buffers, into the project schedule to account for schedule uncertainty. Contingency reserves are the estimated duration within the schedule baseline, which is allocated for identified risks that are accepted and for which contingent or mitigation responses are developed. Contingency reserves are associated with the “known-unknowns,” which may be estimated to account for this unknown amount of rework.
As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. Contingency should be clearly identified in schedule documentation.
[..]
Estimates may also be produced for the amount of management reserve of time for the project. Management reserves are a specified amount of the project duration withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the “unknown-unknowns” that can affect a project. Management reserve is not included in the schedule baseline, but it is part of the overall project duration requirements. Depending on contract terms, use of management reserves may require a change to the schedule baseline.



Which of the following is an output of the Perform Integrated Change Control process?

  1. Project document updates
  2. Organizational process assets updates
  3. Change requests
  4. Deliverables

Answer(s): A

Explanation:

Process: 4.5 Perform Integrated Change Control
Definition: Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



Which of the following is an input to Control Scope?

  1. Project schedule
  2. Organizational process assets updates
  3. Project document updates
  4. Work performance information

Answer(s): D

Explanation:

Process: 5.6 Control Scope
Definition: The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Key Benefit: The key benefit of this process is that it allows the scope baseline to be maintained throughout the project.

Inputs
1. Project management plan
2. Requirements documentation
3. Requirements traceability matrix
4. Work performance data
5. Organizational process assets

Tools & Techniques
1. Variance analysis

Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates



Lessons learned documentation is gathered during which of the following Project Management Process Groups?

  1. Planning
  2. Executing
  3. Closing
  4. Initiating

Answer(s): C

Explanation:

3.7 Closing Process Group
The Closing Process Group consists of those processes performed to conclude all activities across all Project Management Process Groups to formally complete the project, phase, or contractual obligations. This Process Group, when completed, verifes that the defined processes are completed within all of the Process Groups to close the project or a project phase, as appropriate, and formally establishes that the project or project phase is complete.
This Process Group also formally establishes the premature closure of the project. Prematurely closed projects may include, for example: aborted projects, cancelled projects, and projects having a critical situation. In specific cases, when some contracts cannot be formally closed (e.g. claims, termination clauses, etc.) or some activities are to be transferred to other organizational units, specific hand-over procedures may be arranged and finalized.
At project or phase closure, the following may occur:
Obtain acceptance by the customer or sponsor to formally close the project or phase, Conduct post-project or phase-end review,
Record impacts of tailoring to any process,
Document lessons learned,
Apply appropriate updates to organizational process assets,
Archive all relevant project documents in the project management information system (PMIS) to be used as historical data,
Close out all procurement activities ensuring termination of all relevant agreements, and Perform team members’ assessments and release project resources.



Viewing page 111 of 222
Viewing questions 551 - 555 out of 1320 questions


Post your Comments and Discuss PMI CAPM exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!