The key benefit of the Monitoring and Controlling Process Group is the ability to:

  1. establish and manage project communication channels, both external and internal to the project team.
  2. influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.
  3. monitor the ongoing project team against the team performance assessments and the project performance baseline.
  4. observe and measure project performance regularly and consistently to identify variances from the project management plan.

Answer(s): D

Explanation:

• Monitoring and Controlling Process Group. Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.

4.2.3.1 Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. Project baselines include, but are not limited to:
Scope baseline (Section 5.4.3.1), Schedule baseline (Section 6.6.3.1), and Cost baseline (Section 7.3.3.1).

Subsidiary plans include, but are not limited to:

Scope management plan (Section 5.1.3.1), Requirements management plan (Section 5.1.3.2), Schedule management plan (Section 6.1.3.1), Cost management plan (Section 7.1.3.1),
Quality management plan (Section 8.1.3.1), Process improvement plan (Section 8.1.3.2),
Human resource management plan (Section 9.1.3.1), Communications management plan (Section 10.1.3.1), Risk management plan (Section 11.1.3.1), Procurement management plan (Section 12.1.3.1), and Stakeholder management plan (Section 13.2.3.1).
Among other things, the project management plan may also include the following:
Life cycle selected for the project and the processes that will be applied to each phase; Details of the tailoring decisions specified by the project management team as follows:
○ Project management processes selected by the project management team,
○ Level of implementation for each selected process,
○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
Description of how work will be executed to accomplish the project objectives;
Change management plan that documents how changes will be monitored and controlled; Configuration management plan that documents how Configuration management will be performed; Description of how the integrity of the project baselines will be maintained;
Requirements and techniques for communication among stakeholders; and
Key management reviews for content, the extent of, and timing to address, open issues and pending decisions.

The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.



Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

  1. Project Plan
  2. Responsibility Matrix
  3. Issue Log
  4. Scope Document

Answer(s): C

Explanation:

9.4.1.4 Issue Log
Issues arise in the course of managing the project team. An issue log can be used to document and monitor who is responsible for resolving specific issues by a target date.



Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

  1. Project sponsor
  2. Project manager
  3. Person responsible for project scheduling
  4. Person who is most familiar with the task

Answer(s): D



Which of the following is the primary output of the Identify Risks process?

  1. Risk management plan
  2. Risk register
  3. Change requests
  4. Risk response plan

Answer(s): B

Explanation:

Process: 11.2 Identify Risks
Definition: The process of determining which risks may affect the project and documenting their characteristics.
Key Benefit: The key benefit of this process is the documentation of existing risks and the knowledge and ability it provides to the project team to anticipate events.

Inputs
1. Risk management plan
2. Cost management plan
3. Schedule management plan
4. Quality management plan
5. Human resource management plan
6. Scope baseline
7. Activity cost estimates
8. Activity duration estimates
9. Stakeholder register
10. Project documents
11. Procurement documents
12. Enterprise environmental factors
13. Organizational process assets

Tools & Techniques
1. Documentation reviews
2. Information gathering techniques
3. Checklist analysis
4. Assumptions analysis
5. Diagramming techniques
6. SWOT analysis
7. Expert judgment

Outputs
1. Risk register

11.2.3.1 Risk Register
The primary output from Identify Risks is the initial entry into the risk register. The risk register is a document in which the results of risk analysis and risk response planning are recorded. It contains the outcomes of the other risk management processes as they are conducted, resulting in an increase in the level and type of information contained in the risk register over time. The preparation of the risk register begins in the Identify Risks process with the following information, and then becomes available to other project management and risk management processes:
List of identified risks. The identified risks are described in as much detail as is reasonable. A structure for describing risks using risk statements may be applied, for example, EVENT may occur causing IMPACT, or If CAUSE exists, EVENT may occur leading to EFFECT. In addition to the list of identified risks, the root causes of those risks may become more evident. These are the fundamental conditions or events that may give rise to one or more identified risks. They should be recorded and used to support future risk identification for this and other projects.
List of potential responses. Potential responses to a risk may sometimes be identified during the Identify Risks process. These responses, if identified in this process, should be used as inputs to the Plan Risk Responses process.



Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

  1. Cyclic
  2. Progressive
  3. Repetitive
  4. Iterative

Answer(s): B



Viewing page 112 of 222
Viewing questions 556 - 560 out of 1320 questions